Miami weather is synonymous with swimming pool weather. Our sunny climes, year-round heat, and tropical skies practically beg you to lounge by your own pool (maybe with a drink in your hand). Plus, not only are swimming pools highly enjoyable, they also add significant value to a Miami home when it comes to the real estate market. Having a basic understanding of the process of new pool construction in Miami is essential to having the process go smoothly. In this article, trusted Miami pool builders at Swimming Pools of Florida will go over what you can expect when building a new pool.
Standard Timeline For New Pool Construction in Miami
While timelines can vary depending on how large or custom the pool is, it typically takes an average of 8 to 12 weeks to build a pool from beginning to end. Here is a basic outline of what how this time is allotted, and what you can expect when planning, designing, and building out a pool:
Step 1: Start designing with your contractor (1 to 8 weeks)
The first step towards having a pool in your backyard is knowing what you want. What shape do you want it? How big will your pool be? Are you thinking about landscaping around the pool? You can start dreaming up your ideal pool on your own, or with the assistance of a swimming pool designer. Make a list of specific requirements and pictures of pools you like from magazines and Pinterest. Consider the pools of friends and families that you have been to – maybe they’ll give you some inspiration. Take it with you to Miami pool builders you can trust and figure out how to make your dream pool come to life with the contractor.
Step Two: Get the permits (2 to 6 weeks)
The permitting process differs depending on the municipality. This is the tricky part – sometimes permits can take as little as a week, or may end up dragging on for months.
Step Three: Preparing and excavating the land (1 week)
Once you and your contractor have solidified the design and settled on the cost, they will start excavating the land and preparing it for the pool. This may involve removing obstacles like trees and large rocks, or redirecting utility lines. The timeframe for this process depends on how large the pool will be, the weather, and the kind of land you’re building it on.
Step Four: Installing steel, plumbing, and electrical (1 to 2 weeks)
Your contractor will build the steel frame for your pool and install appropriate plumbing and pipes to run the pool pump, filter, and heater. The electrical wiring enables you to switch on components like heaters, lights, and water features.
Step Five: Install the walls and floor (3 to 6 weeks)
How long it takes to install the walls and flooring of the pool depends on which material you are building with. For most pools, it takes around 20 to 60 days.
Step Six: Decorating and finishing (1 to 4 weeks)
If you’re putting in a pool and landscaping at the same time, it can take extra time for these elements to come together. Additional features like waterfalls, decorative tiles, custom lighting, or a patio will also add time.
Step Seven: Filling it up (2 to 3 days)
Filling a pool with water can take up to two days, and installing the filter, pump, and heater takes another two work days. But it’ll be worth it – once this is done, you can cannonball right in.